Templates and records · ISO 27001 · Clause 6.1.3
ISO 27001 risk treatment plan template
What will be done about each risk that is not accepted: with which controls, by whom, by when and what risk remains afterwards, approved by its owner.
In one sentence
The risk treatment plan sets out, for each risk that is not accepted, the option chosen —mitigate, avoid, transfer or accept—, the controls to be applied, the person responsible and the deadline, and the owner’s approval together with their acceptance of the residual risk, which is what clause 6.1.3 e) and f) of ISO/IEC 27001 requires.
- Where the standard requires it
- ISO 27001 · Clause 6.1.3 Clauses follow ISO/IEC 27001:2022; those beginning with “A.” are Annex A controls, required to the extent that the statement of applicability includes them.
- Type of information
- Mandatory record A documented process (6.1.3) and results to be retained (8.3)
- Who fills it in
- Information security manager and risk owners The owner approves the plan and signs off acceptance of the residual risk
- When
- After every risk assessment Progress is reviewed at the security committee and in the management review
- How long it is kept
- Set by the organisation ISO/IEC 27001 sets no periods: it asks you to decide on the retention and disposition of documented information (7.5.3). Covering the three-year certification cycle lets you show the history at recertification.
What the standard requires
What ISO 27001 demands and what it leaves to your judgement
With the risks rated, the standard asks you to choose treatment options, determine the necessary controls, formulate a plan and obtain the risk owners’ approval of the plan and acceptance of the residual risk.
The plan is not the statement of applicability: the SoA says which controls exist and why; the plan says what is done, by whom and when to reach that state. Both draw on the same assessment.
Implementation of the plan is followed up under clause 8: it has to be carried out and its results retained, so that the audit shows what has been done, what is outstanding and why.
Structure
Fields the template should include
- Risk treated and level before treatment
- Treatment option: mitigate, avoid, transfer or accept
- Planned controls or actions (with their Annex A reference, if any)
- Person responsible and target date
- Resources required
- Expected residual risk level
- Owner’s approval and acceptance of the residual risk
- Status and closing date
Example
Example: treating the risk of a provider outage
Company, people and figures are fictitious: the example only shows what a properly completed record looks like.
| Field | Content |
|---|---|
| Risk | R-07 · Level 10, high |
| Option | Mitigate |
| Action T-07 | Replicate the platform in a second region with tested failover (controls 5.30 and 8.14) |
| Owner and deadline | Head of infrastructure · 31 January 2027 |
| Resources | Approved budget of €18,000 a year |
| Expected residual risk | Level 5, acceptable |
| Approval | Operations director, 10 September 2026; accepts the residual risk |
| Status | In progress · 60% |
At the audit
Mistakes auditors commonly flag
- The plan has no dates or owners: it is a list of good intentions.
- There is no record of the owner accepting the residual risk.
- Risks “transferred” to an insurer or a supplier without checking what the contract covers.
- Actions closed in the plan that are not reflected in the statement of applicability.
In Kimobox
How this record is kept in Kimobox
- 1Each action in the plan is assigned to an owner with a date, and the system sends an alert if it slips.
- 2The treatment is recorded alongside the risk and its owner, with their approval.
- 3The management review starts from a template with security incidents and risks already compiled.
Frequently asked questions
What people ask us before getting started
Can a high risk be accepted?
Yes, if its owner accepts it knowingly and it is recorded. The standard does not forbid accepting risks above the criterion; it asks for the decision to be explicit and taken by someone with the authority to take it.
Can the treatment plan and the SoA be the same document?
They can live in the same tool, but they answer different questions. Merging them tends to lose either the follow-up of actions or the justification of controls.
Keep your ISO 27001 records without loose templates
We'll show you the module running with data similar to yours.
Keep exploring
Related pages
Planning
Planning in ISO 27001 means analyzing the risk of each asset and deciding, with judgment, which Annex A…
ISO 27001 statement of applicability template
What the ISO 27001 statement of applicability (6.1.3 d) must contain: necessary controls, justification…
ISO 27001 information security risk assessment template
How to document the information security risk assessment ISO 27001 requires: acceptance criteria, risk…
ISO 27001 information asset inventory template
How to build the information asset inventory required by ISO 27001 control 5.9: asset type, owner, location…
Sources
Where each figure comes from
References to the official text in force. If a standard is revised, this page is updated and the review date says so.
- ISO/IEC 27001:2022 — Information security management systems. Requirements ISO/IEC · 25 October 2022
- ISO/IEC 27005:2022 — Guidance on managing information security risks ISO/IEC · October 2022