Templates and records · ISO 20000 · Clause 8.5.1
ISO 20000-1 request for change (RFC) template
Every modification to a service or a controlled item: what changes, why, what risk it carries, who approves it, how to back it out if it goes wrong and whether it worked.
In one sentence
A request for change records the description of and reason for the change, its classification, the assessment of risks, benefits, feasibility and financial impact, approval by whoever has authority, the planned date communicated, the back-out plan, test results and the review of its effectiveness, because clause 8.5.1 of ISO/IEC 20000-1 requires every request to be recorded and classified and decisions to be taken with the parties involved in line with the change management policy.
- Where the standard requires it
- ISO 20000 · Clause 8.5.1 Clauses are cited using the numbering of ISO/IEC 20000-1:2018, the current edition and the same one the Academy uses.
- Type of information
- Mandatory record Recording and classification of requests for change (8.5.1.2), with the documented policy (8.5.1.1)
- Who fills it in
- Change manager Approved by whoever the policy specifies; significant changes go to a board with the parties involved
- When
- Before any controlled change Emergency changes can be approved through a fast track, but are recorded all the same
- How long it is kept
- Set by the organisation The standard requires control of the retention and disposition of documented information (7.5.3) without setting periods. It is usual to cover at least the three-year certification cycle, or the term of the customer contract if longer.
What the standard requires
What ISO 20000 demands and what it leaves to your judgement
The standard requires a change management policy defining which configuration items are under its control, the criteria for identifying changes with the potential for major impact — which are managed through service design and transition under 8.5.2 — and how emergency changes are handled.
Each request is recorded and classified. The decision is taken with the parties involved, assessing risks, benefits, feasibility and financial impact. Planned dates are communicated, back-out activities are prepared and, where possible, tested, and if the change fails they are applied.
After implementation the effectiveness of the change is reviewed, and change request records are analysed periodically to detect trends.
Structure
Fields the template should include
- Number, date and requester
- Description and reason
- Services and configuration items affected
- Classification: standard, normal, emergency or major impact
- Assessment of risks, benefits, feasibility and financial impact
- Approval and who decides
- Planned window and communication
- Back-out plan and whether it has been tested
- Test results and implementation
- Review of effectiveness and closure
Example
Example: certificate inventory with warning
Company, people and figures are fictitious: the example only shows what a properly completed record looks like.
| Field | Content |
|---|---|
| Change | CHG-26-077 · 22 April 2026 · source: problem PRB-26-021 |
| Description | Register the 46 server certificates as configuration items with an automatic 30-day warning |
| Affects | Configuration database and monitoring tool |
| Classification | Normal · low risk |
| Assessment | No service interruption · internal cost of 3 days' effort · prevents outages like April's |
| Approval | Change advisory board of 24 April |
| Window | 28 April, 19:00-21:00 · communicated to the customer on the 24th |
| Back-out | Disable the warning rule · tested in pre-production |
| Effectiveness | First warning received on 12 June, 30 days before expiry · effective |
At the audit
Mistakes auditors commonly flag
- Changes made in production with no recorded request.
- Emergency changes that are never recorded afterwards.
- Back-out plans that do not exist or have not been tested.
- No subsequent review of whether the change worked.
- The policy does not define which items are under change control.
In Kimobox
How this record is kept in Kimobox
- 1Requests for change are managed as an approval workflow.
- 2Each change keeps its approval, testing and outcome documented in the same workflow.
- 3Configuration items are recorded as versioned assets.
Frequently asked questions
What people ask us before getting started
What is a standard change?
A low-risk, frequent change with a known procedure, which is pre-approved and does not go to the board each time. ISO/IEC 20000-1 does not use that term, but it allows the policy to define which changes are handled that way.
How is an emergency change handled?
The change management policy must define how they are managed. The usual approach is fast approval by an authorised person and a full record afterwards, with its review.
Keep your ISO 20000 records without loose templates
We'll show you the module running with data similar to yours.
Keep exploring
Related pages
Service design and transition
Every change to an IT service must be planned and tested before going into production to minimize risk.
ISO 20000-1 IT service catalogue template
What the service catalogue ISO/IEC 20000-1 requires must include: description, intended outcomes…
ISO 20000-1 service level agreement (SLA) template
What an SLA must contain under ISO/IEC 20000-1 (8.3.3): services, service level targets, workload limits…
ISO 20000-1 service level report template
What the service report ISO/IEC 20000-1 requires must contain: SLA compliance, workload, major incidents…