Templates and records · IATF 16949 · Clause 8.3.4.4
PPAP: IATF 16949 production part approval file
Before supplying in series, the supplier shows the customer that it understands the requirements and that its process, under real conditions, makes conforming parts at the planned rate.
In one sentence
PPAP is the file through which a supplier obtains approval of a production part —design records, FMEA, process flow chart, control plan, MSA, dimensional and test results, initial process studies and the PSW, among others—, because IATF 16949 requires a product and manufacturing process approval process in line with what the customer defines (8.3.4.4), and most customers refer to the AIAG PPAP manual or to VDA 2.
- Where the standard requires it
- IATF 16949 · Clause 8.3.4.4 Clauses are those of IATF 16949:2016, which always applies together with ISO 9001:2015. The AIAG and VDA manuals cited are industry references that apply when the customer requires them; they are not part of the standard.
- Type of information
- Mandatory record Approval required by 8.3.4.4; its content is defined by the customer
- Who fills it in
- Project quality engineering With process engineering, the laboratory and metrology; the PSW is signed by whoever holds designated authority
- When
- Before series start-up And again after product or process changes the customer makes subject to approval
- How long it is kept
- Part life + 1 year For part approvals, tooling records, product and process design records, purchase orders and contracts: for as long as the part is active in production and service, plus one calendar year, unless the customer or a regulatory agency specifies otherwise (7.5.3.2.1).
What the standard requires
What IATF 16949 demands and what it leaves to your judgement
IATF requires a product and manufacturing process approval process conforming to customer requirements to be established and maintained, applied also to products and services bought from suppliers, and approval to be obtained after the manufacturing process has been verified.
The AIAG PPAP manual defines 18 elements and five submission levels; unless the customer says otherwise, the default is level 3, which requires the warrant, samples and supporting data to be submitted. Approval must be sought again after changes in design, process, supplier or location, according to the customer’s criteria.
Part approval records are retained for as long as the part is active in production and service, plus one calendar year (7.5.3.2.1).
Structure
Fields the template should include
- Design records and authorised engineering change documents
- Customer engineering approval, if required
- Design FMEA (if design-responsible) and process FMEA
- Process flow chart and control plan
- Measurement systems analysis studies
- Dimensional, material and performance test results
- Initial process studies
- Qualified laboratory documentation
- Appearance approval report, samples, master sample and checking aids
- Customer-specific requirements
- Signed Part Submission Warrant (PSW)
Example
Example: PPAP for a new part
Company, people and figures are fictitious: the example only shows what a properly completed record looks like.
| Field | Content |
|---|---|
| Part | Seat bracket SA-0331, design level C (fictitious part and customer) |
| Reason | New part · submission level 3 |
| Production run | 300 parts on the series line, with final tooling and operators, 18 March 2026 |
| Dimensional | 62 dimensions measured on 5 parts, all conforming |
| Initial study | Push-out torque: Ppk 1.92 on 125 readings |
| MSA | Torque tester repeatability and reproducibility: 8.4% of tolerance |
| Tests | 240 h salt spray in an accredited laboratory: conforming |
| PSW | Signed on 25 March by the project quality manager |
| Status | Full customer approval on 8 April 2026 |
At the audit
Mistakes auditors commonly flag
- Production run made with tooling or staff that will not be used in series production.
- The FMEA, flow chart and control plan in the PPAP do not match one another.
- Process changes made after PPAP without informing the customer.
- PPAP MSA carried out on a different gauge from the one listed in the control plan.
- PPAP is not required from the company’s own suppliers of critical components.
In Kimobox
How this record is kept in Kimobox
- 1The PPAP file is recorded with its approval before series start-up.
- 2APQP milestones and deliverables for each project are managed with their status, with no loose spreadsheets.
- 3The documents in the file are kept under version control, linked to the FMEA and the control plan.
- 4The submission to the customer and its response are held in the same record.
Frequently asked questions
What people ask us before getting started
What is the PSW?
The Part Submission Warrant: the document that summarises the submission, declares that the parts meet the requirements and is signed by the supplier’s authorised representative. It is the only element submitted at every level.
Which PPAP level must be submitted?
Whichever the customer specifies. In the AIAG manual, level 1 is the warrant only and level 5 includes a review at the supplier’s plant; if the customer does not specify, level 3 is submitted.
When does it have to be repeated?
When the customer requires it after changes: to design, material, process, a component supplier, the manufacturing location, or after a long period without production. Each customer details its cases in its CSRs.
Keep your IATF 16949 records without loose templates
We'll show you the module running with data similar to yours.
Keep exploring
Related pages
Operation
Operation is the core of IATF 16949: advanced product quality planning, parts approval and statistical…
IATF 16949 customer-specific requirements matrix
How to build the customer-specific requirements (CSR) matrix IATF 16949 calls for (4.3.2): requirement…
IATF 16949 supply contingency plan template
What the IATF 16949 contingency plan (6.1.2.3) must cover: risks to supply, response, customer notification…
Process FMEA (PFMEA) template for IATF 16949
How to carry out the process FMEA required by IATF 16949: structure, functions, failure modes, severity…
Sources
Where each figure comes from
References to the official text in force. If a standard is revised, this page is updated and the review date says so.
- IATF 16949:2016 — Quality management system requirements for automotive production and relevant service parts organizations IATF · First edition, October 2016
- Production Part Approval Process (PPAP) (industry reference, not part of the standard) AIAG · 4th edition, 2006
- VDA QMC publications: VDA 2 (production process and product approval) and VDA 6.3 (process audit) (industry reference) VDA QMC · Current editions